Group Created with Sketch. Back to home page

LATEST UPDATES

Overnight closures during June 2026

Overnight closures will be taking place on the A46 between Billesley Crossroads and Bishopton Roundabout over 15 nights between 8 and 26 June.

Our appointed highways contractor, Montel Civil Engineering, is now approaching the final phase of construction for the access roundabout which connects the A46, Drayton Manor Drive and the new internal access road.

To allow the roundabout to be completed, Montel has scheduled a programme of overnight road closures which will take place between 8.00pm to 6.00am over fifteen nights between Monday 8 to Friday 26 June 2026. Please note that these dates and timings remain subject to change.

For residents and businesses located along the section of road that will be closed, including Drayton Manor Drive and Bannatyne Health Club, the schedule of arrangements for access and egress during the overnight closures can be viewed on Montel’s website. Please note that Montel’s schedule is indicative and may be subject to change as the works progress.

The official diversion route will follow the same route used during the previous programme of overnight closures in February 2026 and will redirect through traffic via the A435 and A4189 during the main A46 closure. Montel will install extensive signage to indicate the official diversion route. A copy of the diversion route can also be viewed on Montel’s website via the link above.

The main works will take place during the first fortnight of overnight closures and the final four nights of closures during week commencing on 23, 24, 25 and 26 June have been scheduled to allow contingency for National Highways to complete their statutory safety audit to sign off the scheme.

For residents and local traffic entering or exiting the section of road closed overnight, limited access will be permitted. To view a map of the full diversion route and for more details, please visit Montel’s dedicated scheme website.

We would like to thank the community in advance for their understanding during the upcoming closures and we have sought to minimise disruption where possible by closing the A46 at quieter periods overnight.

We are updating this page with the latest information and key milestones as our work to build Stratford46 Business Park progresses.

Our primary aim is minimising disruption and we want to work closely with the community and key local stakeholders to make sure that everyone is kept updated and informed throughout.

Since the start of construction in September 2025, we have been working to deliver the new access roundabout on the A46 and internal road infrastructure alongside work to survey, connect and divert utilities.

We anticipate that work to construct the new access roundabout which connects Drayton Manor Drive, the A46 and the new internal access road will be completed in Summer 2026 following the next series of planned overnight closures on the A46 between Monday 8 and Friday 26 June.

Our work to deliver on site infrastructure including earthworks, landscaping and the new internal access roads will continue during 2026. Construction of the first buildings is anticipated to start in late 2026.

We will continue to minimise any disturbance caused to our neighbours and would like to reiterate our sincere thanks to the local community for their ongoing patience and cooperation.

Thumbnail 1
Indicative CGI aerial view (may be subject to change)

Indicative timeline of key activities

Activity Approx. start Approx. end
New Access Roundabout Summer 2025 Late 2026
STW water diversion July 2026 Late 2026
On site infrastructure works Spring 2027 Early 2028
Utility connections Late 2026 Late 2027
Construction of first building(s) 2028 TBC

Latest news

Severn Trent Water main diversion

Between early July and November 2026 Severn Trent Water’s appointed contractor Avove Utilities will be carrying out work to divert the twin main water supply that runs through the Stratford46 Business Park site in preparation for the infrastructure works that will take place in 2027.

Read more
Launch of Stratford46 Community Fund – November 2025

Launch of Stratford46 Community Fund – November 2025

We are pleased to announce the launch of the Stratford 46 Community Fund which we have established in partnership with the Heart of England Community Foundation to support local charities and community groups surrounding Stratford46 Business Park.

Read more

Submission of minor planning applications – October 2025

Construction at Stratford46 Business Park continues to progress well and work to date has involved setting up our site compound and undertaking a programme of surveys along the A46, which has required the use of temporary overnight traffic management to allow our teams to work safely.

Read more

Overnight lane closures on the A46

One of our first activities from Summer 2025 has been conducting overnight surveys alongside the A46, which has required the use of temporary traffic lights and lane closures overnight to enable work to take place safely while keeping the road open.

Read more

Start of construction – September 2025

Construction work for the new access roundabout is now underway and we are committed to delivering this work with minimal disruption or delay.

Read more

Keeping in touch

We remain committed to keeping the community updated as the construction progresses and to give you advance notice of key activities such as any future road closures. Minimising disruption is our primary aim while we deliver Stratford46 Business Park.

To stay up to date on the very latest progress at Stratford46 Business Park, please register for updates here.